Thursday, December 15, 2016

HCA STREAM RESTORATION UPDATE

Project Manager WSSI confirmed late last week that streambed reconstruction work was substantially complete by December 1, and that additional new erosion control planting is scheduled to start mid-December 2016.  In addition, footbridge removal and replacement will be delayed pending Fairfax County re-approval of an expired permit within the next few weeks.  Full completion, including clean-up of the staging area, is now planned for February 2017.