Updated May 2, 2013
BLOCKS 1-3 ASPHALT PATHWAY RECONSTRUCTION
HCA Leads: Michael Smith, Kim Hendon/TWC
Multiple proposals received April 17, 2013
Contract to Finley Asphalt & Sealing Inc.
Work to start May 9, 2013
BLOCKS 1-3 COMMON AREA POWERWASH
HCA Leads: Michael Poss, Kim Hendon/TWC
2012 contract to Spray Services, work completed May 2012
2013 contract to Spray Services, work to start May 13, 2013
Possible as annual maintenance pending HCA review and approval
BLOCKS 1 AND 3 SWINGSET REPLACEMENT
HCA Leads: Ralph Youngren, Michael Smith, Kim Hendon/TWC
Swingset contract to Reston Painting & Contracting
Sitework contract to Blade Runners Inc.
Swingsets removed November 2012
Work completed April 2013
BLOCKS 1-3 PAVEMENT REPAIR
HCA Leads: Blake Travis, Kim Hendon/TWC
Contract to Dr. Pothole
Work completed Summer 2012
BLOCKS 1-3 LAMP POST REFINISHING
HCA Leads: Michael Smith, Kim Hendon/TWC
Contract to Reston Painting & Contracting
Work completed Summer 2012
BLOCK 3 EIFS CLEAN/PAINT AND RAILING REPAIR
HCA Leads: Ralph Youngren, Sara Bradley, Kim Hendon/TWC
Contract to Reston Painting & Contracting
Work completed 2012
BLOCK 3 MEADOW BENCH REPLACEMENT
HCA Leads: Ralph Youngren
Pending additional HCA review
BLOCKS 1-3 FIRE LANE CURB PAINT
HCA Leads: Kim Hendon/TWC
Received Reston Painting & Contracting estimate
Pending HCA review and approval